The redevelopment of 9–11 Elmer Approach, Southend‑on‑Sea, involved the addition of two new floors to an existing 10‑storey structure as part of its conversion into a 108‑room hotel.
To accommodate the increased loads from the new levels, columns throughout the building required strengthening. Freyssinet was appointed to strengthen 52 columns across four floors. The scope included preparing the existing columns, installing formwork, and casting in‑situ Ultra‑High Performance Fibre Reinforced Concrete (UHPFRC) shells to enhance column capacity and ensure long‑term structural performance.
-
ClientRedRock Developments
-
DesignerFreyssinet
-
ScopeExoLeaf® UHPFRC column strengthening
-
Columns strengthened52
The scope
Freyssinet’s Technical Solutions team designed the ExoLeaf® UHPFRC strengthening system and defined the site works sequence, which included the installation and operation of a forced‑action mixing plant.
The surfaces of each column were prepared in order to get the aggregate exposed to allow bonding between the existing concrete and the Ductal material.
- A number of proprietary ‘spiders’ (small steel plates) were installed in all four faces of each column.
- The UHPFRC pouring would be from the level above the column, so a 100mm hole was cored close to each column.
- Following surface preparation, spider installation and coring of the slab, the formwork was installed and secured.
- The specialist mixing plant for the concrete, including a metallic fibres silo, conveyor belt, water collection unit was delivered and commissioned on site.
- The fresh UHPFRC was then unloaded into petrol wheelbarrows and taken to the pouring location using a hoist. As the quantity of concrete remains modest, simple handling means could be used, generating more savings.
- Once the UHPFRC is poured it was cured for seven days before striking the formwork.
- The top kicker of the columns (available gap for pouring the UHPFRC) was then cast using R4 high class repair concrete.
The benefits of ExoLeaf®
- Reduced percussion drilling, and all associated issues: dust, noise, HAVS, microcracking of the existing columns.
- Reduced quantity of materials to be delivered on site (no rebars, less concrete). This in turn reduced the impact on the residents and nearby premises.
- Reduced size of the finished columns, therefore maximising the living space in the refurbished building.
- Fast construction on site providing benefits to the Client. Site works were carried out within the site boundaries, controlled by the Client. Freyssinet works were undertaken over level 3 to level 9 of the building and segregated from the public.
Contact us
You have a question about our solutions or you already have a project in mind?
Email info@freyssinet.co.uk, call 01952 201901 or complete the form below.